Precast Concrete Installation — 25-Story Residential Tower
Li Qiang, we're installing Level 8 today — precast concrete shear walls and composite slabs. Each wall panel is 2.8m high, 3.6m wide, 200mm thick, weight approximately 5 tons. The connection between wall panels uses grouted sleeve connectors. The rebar from the lower panel protrudes 200mm and inserts into the sleeves cast in the upper panel. Then we inject high-strength, non-shrink grout under pressure to fill the annular space. This connection is the structural backbone — if the grouting fails, the wall panels are not structurally continuous.
Li Qiang,今天装第8层——预制混凝土剪力墙和叠合板。每块墙板 2.8m高、3.6m宽、200mm厚、约5吨重。墙板间用灌浆套筒连接。下层 墙板钢筋伸出200mm插入上层墙板的套筒。然后高压注高强无收缩灌浆料 填充环形空间。这个连接是结构脊梁——灌浆失败则墙板不连续。
Correct. Tom, you'll witness the grouting. The critical parameters: grout flow cone test must be 300-350mm before we start — if it's too thick, it won't fill the sleeves; too thin, and the strength drops. Injection pressure 0.8-1.0 MPa from the bottom port. We inject until grout flows cleanly from the top outlet port of each sleeve. Every sleeve must be verified — if the top port doesn't flow, the sleeve is not full. We're grouting panel PW-8A first — it has 12 sleeves, six on each vertical edge.
对。Tom,你见证灌浆。关键参数:灌浆料流动锥试验300-350mm才能 开始——太稠填不满套筒、太稀强度降。注浆压力0.8-1.0MPa从底部注口 注入。注到每个套筒顶部出浆口流出干净浆液为止。每根套筒必须验证—— 顶部不出浆、套筒就没满。先注PW-8A板——12个套筒、每条竖边6个。
Panel PW-8A is placed on shims. Plumb verified — 2mm deviation on a 2m level, within 5mm tolerance. Braces installed. Now mixing grout... flow cone test: 320mm. Within range. Starting injection on sleeve 1, bottom port.
PW-8A板坐浆垫片。垂直校核完成——2m水平尺偏差2mm、在5mm公差内。 斜撑装好。现在拌灌浆料……流动锥试验:320mm。范围内。开始套筒1底部 注浆。
(watching the outlet ports) Sleeve 1: top port flowing — full. Sleeve 2: flowing. Sleeves 3, 4, 5, 6... all flowing. Wait — sleeve 9 top port is NOT flowing. Ivan, stop injection on sleeve 9. Check the outlet port — it might be blocked.
(看出浆口)套筒1:顶部出浆——满。套筒2:出浆。3/4/5/6……全出浆。 等等——套筒9顶部不出浆。Ivan,停套筒9注浆。查出浆口——可能堵了。
(checks port with a wire probe) Found it — a small piece of foam from the sleeve cap was left in the port during factory casting. The foam blocked the outlet. Clearing it now... (probes the port, foam piece comes out) Re-starting injection — outlet is flowing. Sleeve 9 filled. All 12 sleeves confirmed full. Panel PW-8A grouting complete and verified. Total grouting time: 18 minutes.
(用细钢丝探出浆口)找到了——工厂浇筑时一小块泡沫从套筒盖残留在 了端口里。泡沫堵了出浆口。现在清理……(探通、泡沫出来)重启注浆—— 出浆了。套筒9满。12根全满确认。PW-8A板灌浆完成并验证。总灌浆时间 18分钟。
Wet Area Ponding Test — Pre-Handover Inspection
Ahmed, this is the pre-handover wet area inspection. Every bathroom and kitchen in all 200 apartments must pass a 24-hour ponding test. The procedure: plug the floor drain, fill the room with water to a depth of 30-50mm, mark the water level, and check after 24 hours. Any drop in water level or any sign of moisture on the ceiling of the unit below is a fail. Let's start with Unit 1205 — the master bathroom.
Ahmed,交付前湿区检查。全部200套的每个卫生间和厨房必须通过 24小时蓄水试验。程序:堵地漏、灌水30-50mm深、标记水位、24小时后 检查。水位下降或下层天花板任何潮湿迹象都是不合格。从1205单元 主卫开始。
1205 master bathroom was filled yesterday at 14:00. Water depth: 40mm. I marked the water level with tape on the wall. It's now 14:15 the next day — 24 hours and 15 minutes. The water level is at the tape mark — zero visible drop. Let's check Unit 1105 below. (goes downstairs) Ahmed, the ceiling of 1105 below the 1205 bathroom — completely dry. No stains, no dampness, no peeling paint. Moisture meter reading: 4.2% — that's normal equilibrium moisture for the concrete slab. Unit 1205 master bathroom — PASS.
1205主卫昨天14:00灌水。水深40mm。墙上胶带标记了水位。现在次日 14:15——24小时15分钟。水位在标记线——零可见下降。查楼下1105。 (下楼)Ahmed、1105吊顶在1205卫生间下方——完全干燥。无污渍、无潮湿、 无剥落。湿度仪读数:4.2%——混凝土板正常平衡含水。1205主卫通过。
Good. Let me check the shower area specifically — that's where most leaks happen. The shower floor-to-wall junction and the drain penetration are the critical points. (inspects with flashlight) The silicone seal at the wall-floor joint is intact and tooled smooth. No gaps around the drain flange. OK, accepted. Let's move to Unit 1208 — the kitchen.
好。我重点查淋浴区——那是最多渗漏的地方。淋浴区地墙交接和地漏 穿透是关键点。(手电检查)墙地接缝硅酮胶完好抹平。地漏法兰周围无 间隙。好、验收。看1208厨房。